Taylor Farms

TAYLOR FARMS

Overview

  • Taylor Farm purchased a former jams and jellies plant, which in turn had to be converted into a high-grade USDA retail processing facility.

Project Highlights

  • The project included complete demolition of an existing facility with the exception of three exterior building walls, as well as construction of a state-of-the-art refrigerated facility for the production of prepared salads and cut vegetables.
  • This design-build project was completed on a fast-track schedule in less than 9 months in spite of challenging existing site conditions which included several adjacent properties that were located in close proximity.

 

Ocean Spray

OCEAN SPRAY

Overview

  • When global demand for Ocean Spray dried cranberries doubled within three years and was projected to double once again, the company made its largest capital investment in a manufacturing facility to date with a 130,000 SF expansion that doubled the plant’s size to 440,000 SF. The plant produces both sweetened dried cranberries and cranberry juice concentrates.

Project Highlights

  • The facility incorporated some of the latest technologies in energy and environmental efficiency, including a wastewater  treatment facility, energy-efficient lighting, and an expansion of a system that converts methane from the Veolia Cranberry Creek Landfill into clean energy to power the plant.
  • A new fully-racked warehouse for both ingredients and finished goods increased storage capacity. The expansion enabled the plant to produce more than 30 million pounds of sweetened dried cranberries per year.
  • Major accomplishments of the project included design and implementation of 5S standards in creating state-of-the-art maintenance shop and quality control lab spaces.

 

Dole

DOLE

Overview

  • Dennis Group teamed with Dole to develop the design for a forward processing plant in the Midwest. Dennis Group worked with Dole to develop the process and then designed the facility around the needs of that process.

Project Highlights

  • Dennis Group assisted Dole with site selection, and once the site selection was finalized, developed the site, executed preliminary and detailed engineering of the building, erected the building, designed the process and process utilities, installed the process equipment, and commissioned the facility to operate all in under one year.
  • In addition to the original facility, the Dennis Group executed two expansions to the Dole Springfield facility. The Dennis Group provided design/build services for a 30,000 SF warehouse expansion, and for a 25,000 SF expansion to house processing and packaging of fresh cut fruit.

 

Dole

DOLE

Overview

  • Dennis Group provided complete site, facility and process design, procurement and installation services for this greenfield site.

Project Highlights

  • The project included development of a 100 acre site and construction of a 280,000 SF processing facility to house production equipment for the making of prepared salads and cut vegetables.
  • Major accomplishments of the project include balancing a site that required over 500,000 cubic feet of cut and fill, working with the state to install a 100,000 gallon waste water retention tank, installation of a 2000 ton ammonia refrigeration system, and installation of equipment to produce 500,000 lbs. of salad per day.

 

Dole

DOLE

Overview

  • Dennis Group teamed with Dole for the design and construction of a greenfield operation in Helsingborg, Sweden.

Project Highlights

  • Included was development of a 4-acre site, and the design and construction of a 55,000 SF facility for the processing and packaging of ready-to-eat fresh salads.
  • This project also included the design and installation of four automated processing and packaging lines, including the first fully automated drying operation within the Dole organization.
  • Additionally, the entire project was designed around an efficient future building expansion that would incorporate a total of 8 processing lines